Before starting construction below the high-water mark of navigable waters, what is required?

Approval from local government

Application to the Minister of Fisheries and Oceans Canada

Before commencing any construction activities below the high-water mark of navigable waters, it is essential to obtain an application to the Minister of Fisheries and Oceans Canada. This requirement is rooted in the protection of navigable waters and the public's right to navigate these waters freely. The Minister of Fisheries and Oceans oversees matters related to fish habitat, navigation, and environmental protection in waterways, ensuring that any construction does not hinder navigation or negatively impact aquatic ecosystems.

Navigable waters are protected under the Navigable Waters Protection Act, which mandates that permission must be secured from the appropriate authorities before any construction project that could affect navigation is initiated. This ensures that any potential impacts on the waterway and its use are assessed and mitigated.

While approval from local government, agreements with neighboring landowners, and environmental assessments can be necessary for various aspects of construction, the specific requirement for activities below the high-water mark of navigable waters is the application to the Minister of Fisheries and Oceans Canada. This emphasizes the significance of safeguarding navigable waters as a vital shared resource.

Get further explanation with Examzify DeepDiveBeta

Agreement from the neighboring landowners

Environmental impact assessment